Project Description

For the Montefiore Hutch Metro Center MRI project in Bronx, NY, Bladykas Engineering leveraged its experience in healthcare infrastructure to design and install new mechanical and electrical systems to support the MRI machine, along with coordinating the lighting design. The project was executed in phases to minimize downtime, and included the addition of a VAV system, emergency purge fans, a chilled water CRAC system, and a quench vent system. The team also conducted a comprehensive fire alarm system study to address compliance issues. A significant aspect of the project was the replacement of an existing extremity MRI with a new large-bore MRI, all of which was completed on an accelerated schedule.